The duration of the project will be 30 months. The WP3000 planning and milestones are defined and scheduled as follows :




 
Months
Milestones
To
Sept.1st, 1998
  • MFSPP starts
  • To + 6 months
    March 1st, 1999
  • End of www server development : subtask 3410

  • End of mean sea surface calaculation : subtask 3120

  • End of NRT SST product development : task 3200

  • To + 9 months
    June 1st, 1999
  • End of orbit reduction and mapping algorithm development : subtask 3310

  • Start processing and distribution of Remote Sensing data for the TOP-2 period, altimetry and SST in delayed time : task 3300 and subtask 3420.
  • To + 12 months Sept. 1st, 1999
  • End of comparison of NRT and delayed time altimeter data : subtask 3130
  • To + 15 months Dec. 1st, 1999
  • Start Near Real Time Remote Sensing Data processing and distribution : task 3300 and 3420.
  • To + 21 months June 1st, 2000
  • End of NRT Remote Sensing data distribution : subtask 3410
  • To + 30 months March 1st, 2001
  • End of NRT Remote Sensing data analysis : task 3300
  • End of MSPP



  •  